Sports hall development update

Our
Sport Hall development site is now a hive of activity with various trades
working alongside each other to ensure the building is handed over to the
school at the end of June 2016. 

We
have received many compliments on the sympathetic choice of external materials
used to break up the mass of the main hall. The full structure is now in situ
and you can easily see the true shape and size of the development which nestles
nicely into the southern banks of the school site. Of special note is the
internal viewing area which has been considerately designed to allow spectators
to watch main hall activities taking place.    Over the next few
weeks the contractor will be working on grading the ground level around the
sports hall back into the playing field levels. This has to be a balanced
approach of safety and not losing green pitch space.

Once
the Sports Hall is handed over to the school, the contractor will refurbish the
tennis court, complete the necessary paths and make good disturbed ground.